Dear Readers, IBPS is conducting Online Examination for the recruitment of Clerical Cadre. Preliminary Examination of IBPS Clerk was scheduled from 2nd Dec 2017. To enrich your preparation here we have providing new series of Practice Questions on Quantitative Aptitude. Candidates those who are appearing in IBPS Clerk Exam can practice these questions daily and make your preparation effective.
Quantitative Aptitude Questions – Time and Work
[WpProQuiz 793]
Click “Start Quiz” to attend these Questions and view Solutions
For More Practice Quantitative Aptitude Questions for IBPS Clerk Exams – Click Here
1). 7 men can finish a piece of work in 21 days. 14 men started working and after 5 days they were replaced by 8 women. These 8 women finished the remaining work in 24 days. In how many days can 8 women finish the whole work?
- 56 7/11
- 45 9/11
- 43 5/11
- 48 3/11
- None of these
2). 20 men can complete a piece of work in 16 days, after 5 days from the start of work , some men left. If the remaining work was completed by remaining men in 18 1/3 days, how many men left after 5 days from the start of work?
- 12
- 5
- 8
- 7
- None of these
3). A builder undertook to finish a work in 124 days with the help of 120 men. After 64 days he found that 2/3 of the work had already been done. How many men should be discharged now so that the work can be finished on time?
- 64
- 56
- 48
- 50
- None of these
4). A man, a woman and a boy can do a piece of work in 3,4 and 12 days respectively. How many boys must join with 1 man and 1 woman to complete the work in 1 day?
- 7
- 4
- 6
- 5
- None of these
5). 25 women earned 143500 by working 35 days. How many men must work for 12 days to receive 70848 provided the daily wages of a man is twice that of a woman?
- 18
- 20
- 15
- 22
- None of these
6). If x men can do a piece of work in 8 days and (x+4) men can do the same work in 6 days, then x is?
- 12
- 14
- 16
- 10
- None of these
7). A,B and C can do a piece of work in 15,20 and 30 days. They undertake to complete the work for Rs. 810. Howmuch share of A exceeds that of B?
- 270
- 360
- 90
- 180
- None of these
8). 20 men can do a piece of work in 20 days. Five days after they started the work, 10 more men joined them. How many days will they now take to complete the remaining work?
- 9 days
- 10 days
- 8 days
- 12 days
- None of these
9). Prem can do a piece of work in 32 days. Ragu can do the same piece of work in 42 days and Nandan in 36 days. Prem and Nandan worked for 6 days and handed it to Rishi. Rishi worked for some days and handed it again to Prem and Nandan 10 days before completing the work. For howmany days did Rishi work?
- 5 1/3
- 4 2/7
- 5 1/8
- 2 1/3
- None of these
10). If 6 men and 8 boys can do a piece of work in 10 days. While 26 men and 48 boys do the same piece of work in 2 days, how much time will be taken by 15 men and 20 boys for doing the same piece of work?
- 4 days
- 5 days
- 4 ½ days
- 3 days
- None of these